LDHT Engineering, power system engineering consultancy

Market

Industry

Energy-intensive sites, electrified processes, ageing substations. We check what the site network can handle and what needs to be modified.

Electrifying a process often multiplies the power demand. RTE plans to add nearly 9 GW of ready-to-connect capacity around Dunkirk, Le Havre and Fos by 2029 (RTE, July 2026).

On the site, two questions arise. The first concerns the connection to the public grid, the second the capacity of the internal network (substations, protection, cables, earthing) to take the load without any loss of safety.

Common situations

Many industrial networks have been built in layers, with thirty years of extensions, drawings that no longer match and settings copied from one feeder to the next. Before calculating, we rebuild the network as it actually is.

New loads (arc or induction furnaces, electrolysers, high-power compressors, large drives) cause voltage dips on starting, harmonics and flicker. They also raise the question of the short-circuit withstand of existing equipment.

For personnel safety, live working, or work near live parts, requires knowing the incident energy at each switchboard. This energy depends directly on the protection settings.

MV connection to the Enedis network

Most industrial sites are connected at MV to the public distribution network. The point-of-connection substation falls under NF C 13-100, the internal installation under NF C 13-200. The main protection must be selective with the Enedis feeder. Its settings are framed by the network operator, and a setting error trips the public feeder instead of the site circuit-breaker.

01What we do

Studies

  • Connection of new loads
  • Large motor starting
  • Harmonics from drives and furnaces
  • Protection coordination and arc flash
  • Voltage plan and reactive compensation

Services

  • Substation and protection audits
  • Relay, tap changer and automation testing
  • Technical support to design teams

02Examples

Extract from a 13.8 kV MV single-line diagram of a protection plan
Fig. 01Extract from the single-line diagram of a 13.8 kV MV protection plan.Anonymised deliverable
Harmonic voltages at the 20 kV busbar, with and without capacitor bank0 %1 %2 %3 %4 %5 %Uh / Unh5h7h11h13h17h19h23h25with capacitors: THD ≈ 4.7 %without capacitors: THD ≈ 2.9 %6-pulse rectifier 3 MW, Ih = I1 / h
Fig. 023 MW rectifier on a 20 kV, 250 MVA network with a 5 Mvar capacitor bank. The 7th harmonic is amplified and THD rises from 2.9 to 4.7 %.Worked example
Time-current curves plotted in ETAP
Fig. 03Protection coordination curves plotted in ETAP.Anonymised deliverable

03Our offer

Usual content of an offer for this type of assignment. The exact scope, deliverables and price are set in the quotation.

  1. Package 1Survey of the existing installation

    Substation visits, survey of nameplates and settings in place, collection of drawings.

  2. Package 2Network model

    Network rebuilt in ETAP or PowerFactory, with assumptions in writing.

  3. Package 3Calculations

    Connection of the new load, short-circuit, protection coordination, harmonics, arc flash, as required.

  4. Package 4Action plan

    Actions ranked by priority and cost, settings to apply, equipment to replace.

04How we work

  1. 01Survey of the existing installation

    Drawings, nameplates, settings read from the relays, substation visits.

  2. 02Network model

    Network rebuilt in ETAP or PowerFactory, with assumptions in writing.

  3. 03Calculations

    Load connection, short-circuit, protection coordination, harmonics, arc flash as required.

  4. 04Action plan

    Measures ranked by priority and cost, settings to apply, equipment to replace.

05References

Heavy industry

Electrical installation audit

Condition of substations and protection, identified risks and costed recommendations, ranked by priority.

Industrial site

Protection coordination and relay verification

MV protection coordination and on-site check of the settings.

63 and 225 kV substations

Protection relay testing

Differential protection and on-load tap changers. Testing carried out with Volt Expertise.

All references

06Frequently asked questions

How do you work without up-to-date drawings?

We rebuild the network from surveys and the available documents, and we write down the assumptions made.

Do you work during plant shutdowns?

Yes, relay testing and checks are scheduled within your outage windows.