LDHT Engineering, power system engineering consultancy

Market

Data centres

225 / 20 kV substations of several hundred MVA, with redundancy at every level. We carry out the studies and the technical support, from the connection request to energisation.

For a data centre, the connection lead time often weighs on the whole schedule. RTE lists more than 200 projects, nearly 33 GW, waiting for a high-voltage connection, and plans to serve the most advanced projects first (RTE, July 2026). A complete and consistent technical file from the request stage helps keep your place in the queue.

Points of attention

The voltage plan is a frequent problem. With two 225 / 20 kV transformers loaded at half in normal operation and at full load in N-1, the on-load tap changer (OLTC) range must cover the full contractual voltage range of the upstream network. We have already found it insufficient on advanced projects.

On generator backup, the short-circuit current drops sharply and protection set for the grid no longer sees some faults. A dedicated settings group or suitable functions are then needed, and must be verified.

Re-energising a complete data hall means energising dozens of transformers at the same time, with inrush current, a voltage dip and a risk of nuisance tripping. These phenomena are calculated before commissioning.

An HV substation located in the middle of a campus creates an earth potential rise to be controlled with respect to buildings, fences and telecom cables leaving the site.

We work for the operator or the developer, with no ties to equipment suppliers or contractors, or in support of a general contractor.

01What we do

Studies

  • Load flow, N-1 and voltage plan
  • Short-circuit, including generator backup operation
  • HV / MV protection plan
  • Earthing system and telecom compatibility
  • Harmonics from UPS units and power supplies
  • Transformer energisation

Services

  • Owner's engineering and design review (VISA) of substations
  • Follow-up of testing and commissioning
  • Relay configuration and testing

02Examples

Schematic diagram of a 225 / 20 kV point-of-connection substation with two transformersRTE incomer 1Q1RTE incomer 2Q2225 kVQ11TR1225 / 20 kVQ21Q12TR2225 / 20 kVQ2220 kVbus couplerD1D2D3D4to IT halls / UPS87T50/51
Fig. 01Schematic diagram of a 225 / 20 kV point-of-connection substation with two transformers.
Load flow results for a 225 / 20 kV substation with three feeders: voltages, power flows, loading225 kV · 1.000 puTR 80 MVA · tap 2.5 %loading 54 %P 39.9 MWQ 17.0 Mvar20 kV · 1.000 puD1 · 3 km12 MW · cos φ 0.950.985 puD2 · 5 km18 MW · cos φ 0.930.961 puD3 · 2 km9 MW · cos φ 0.960.993 puCalculation result(Gauss iteration)
Fig. 02Load flow of a 225 / 20 kV substation with three feeders, showing the voltage at the end of each feeder, the power flows and the transformer loading (54 %).Worked example
Protection zones of a 225 / 20 kV substation: line, busbars, transformer, feeders21 · 87L line87B 225 kV87T · 64REF87B · 50/51 20 kV50/51 · 50N/51N · 67N225 kV lineTR 225 / 20 kVMV feedersZones overlap around the circuit-breakers: no point of the substation is unprotected.
Fig. 03Protection zones of a 225 / 20 kV substation. Each zone is bounded by its current transformers, and the zones overlap around the circuit-breakers.Schematic diagram
HV switchgear: instrument transformers and post insulators in a substation
Fig. 04HV switchgear, instrument transformers and post insulators.Photo

03Our offer

Usual content of an offer for this type of assignment. The exact scope, deliverables and price are set in the quotation.

  1. Package 1Connection application

    Technical data requested by the network operator, checked for consistency, and schematic diagram.

  2. Package 2Design studies

    N and N-1 load flow, short-circuit, protection plan, earthing system, harmonics, according to the agreed scope.

  3. Package 3Review of the contractor's studies

    Design review (VISA) of execution documents, deviations ranked blocking, major, minor.

  4. Package 4Testing and energisation

    Follow-up of factory and site tests, check of settings, attendance at the first energisation.

04How we work

  1. 01Connection application

    Power, load profile, phasing and schematic diagram, with consistent data, as the network operator asks for them.

  2. 02Design studies

    N-1 load flow, short-circuit, protection plan, earthing, harmonics from UPS units and power supplies.

  3. 03Review of the contractor's studies

    Design review (VISA) of execution documents, with deviations ranked by severity.

  4. 04Testing and commissioning

    Follow-up of factory and site tests, check of settings, first energisation.

05References

Data centre operator

225 kV GIS substation

Design review and review of the studies (VISA). We found deviations on the voltage transformers and on trip circuit redundancy.

General contractor

Protection plan, 240 MVA data centre

Selection of protection functions, current transformer sizing, settings, follow-up of testing through to commissioning.

Data centre, Île-de-France

225 / 20 kV substation

Review of the drawings for the entire substation package against the client's requirements, with the list of major deviations.

Data centre, Île-de-France

Load flow campaign on an ETAP model

Audit of the existing scenarios and sweep of upstream voltage × configurations. The on-load tap changer range of the 225 kV transformers proved insufficient.

Data centre campus

Earthing systems

Earth grid, step and touch voltages, earth potential rise, compatibility with telecom networks.

All references

06Frequently asked questions

Do you work for the project owner or for the contractor?

Both. We prefer to work for the project owner, and we have no ties to any supplier or contractor.

Can you take over a model built by another consultancy?

Yes. We check it first (data, topology, scenarios) before using its results.

Do you cover operation on standby generators?

Yes. We calculate short-circuit currents in backup mode, adapt the settings and study generator starting and load pick-up.

07See also

For a project, give us the voltage, power, location and deadline in a few lines.