Data centre operator
225 kV GIS substation
Design review and review of the studies (VISA). We found deviations on the voltage transformers and on trip circuit redundancy.
Market
225 / 20 kV substations of several hundred MVA, with redundancy at every level. We carry out the studies and the technical support, from the connection request to energisation.
For a data centre, the connection lead time often weighs on the whole schedule. RTE lists more than 200 projects, nearly 33 GW, waiting for a high-voltage connection, and plans to serve the most advanced projects first (RTE, July 2026). A complete and consistent technical file from the request stage helps keep your place in the queue.
The voltage plan is a frequent problem. With two 225 / 20 kV transformers loaded at half in normal operation and at full load in N-1, the on-load tap changer (OLTC) range must cover the full contractual voltage range of the upstream network. We have already found it insufficient on advanced projects.
On generator backup, the short-circuit current drops sharply and protection set for the grid no longer sees some faults. A dedicated settings group or suitable functions are then needed, and must be verified.
Re-energising a complete data hall means energising dozens of transformers at the same time, with inrush current, a voltage dip and a risk of nuisance tripping. These phenomena are calculated before commissioning.
An HV substation located in the middle of a campus creates an earth potential rise to be controlled with respect to buildings, fences and telecom cables leaving the site.
We work for the operator or the developer, with no ties to equipment suppliers or contractors, or in support of a general contractor.

Usual content of an offer for this type of assignment. The exact scope, deliverables and price are set in the quotation.
Technical data requested by the network operator, checked for consistency, and schematic diagram.
N and N-1 load flow, short-circuit, protection plan, earthing system, harmonics, according to the agreed scope.
Design review (VISA) of execution documents, deviations ranked blocking, major, minor.
Follow-up of factory and site tests, check of settings, attendance at the first energisation.
Power, load profile, phasing and schematic diagram, with consistent data, as the network operator asks for them.
N-1 load flow, short-circuit, protection plan, earthing, harmonics from UPS units and power supplies.
Design review (VISA) of execution documents, with deviations ranked by severity.
Follow-up of factory and site tests, check of settings, first energisation.
Data centre operator
Design review and review of the studies (VISA). We found deviations on the voltage transformers and on trip circuit redundancy.
General contractor
Selection of protection functions, current transformer sizing, settings, follow-up of testing through to commissioning.
Data centre, Île-de-France
Review of the drawings for the entire substation package against the client's requirements, with the list of major deviations.
Data centre, Île-de-France
Audit of the existing scenarios and sweep of upstream voltage × configurations. The on-load tap changer range of the 225 kV transformers proved insufficient.
Data centre campus
Earth grid, step and touch voltages, earth potential rise, compatibility with telecom networks.
Both. We prefer to work for the project owner, and we have no ties to any supplier or contractor.
Yes. We check it first (data, topology, scenarios) before using its results.
Yes. We calculate short-circuit currents in backup mode, adapt the settings and study generator starting and load pick-up.
For a project, give us the voltage, power, location and deadline in a few lines.